A` completes a work in 10 days, while lB and C complete it in 12 and 15 days respectively. In how many days can `A, B` and C` together complete the work ?

examrobotsa's picture
Q: 89 (CAPF/2009)
‘A' completes a work in 10 days, while lB and ‘C complete it in 12 and 15 days respectively. In how many days can 'A, ‘B' and ‘C' together complete the work ?