50 men or 80 women can finish a job in , 50 days. A contractor deploys 40 men and 48 women for this work, but after every duration of 10 days, 5 men and 8 women are removed till the work is completed. The work is completed in:

examrobotsa's picture
Q: 142 (IAS/2004)
50 men or 80 women can finish a job in , 50 days. A contractor deploys 40 men and 48 women for this work, but after every duration of 10 days, 5 men and 8 women are removed till the work is completed. The work is completed in:

question_subject: 

Maths

question_exam: 

IAS

stats: 

0,1,4,1,1,3,0

keywords: 

{'duration': [0, 0, 1, 0], 'contractor': [0, 0, 1, 0], 'days': [0, 0, 2, 0], 'men': [4, 3, 12, 9], 'work': [1, 1, 10, 7], 'job': [0, 1, 2, 1], 'women': [9, 8, 22, 46]}

The problem is a work-efficiency problem where the efficiency of men and women varies. To complete the job, 50 men take 50 days, so the total work can be represented as 50*50 = 2500 man-days. Similarly, 80 women can complete the job in 50 days, which is 80*50 = 4000 woman-days.

Now, the contractor starts with 40 men and 48 women. He removes 5 men and 8 women every 10 days until the work is done. Therefore, in the first 10 days, (40 men + 48 women) work for 10 days amounting to 400 man-days and 480 woman-days. This process continues, with a decrease in manpower every 10 days.

As 2500 man-days work equals to 4000 woman-days work, one can convert the woman-days work to man-days work or vice versa, and calculate when the total work (2500 man-days or 4000 woman-days) is completed.

Doing so would reveal that the total work would be completed in 50 days, making option 2 the correct answer.

Practice this on app