In a significant climate responsive project, in which one of the following places, recently an abandoned thermal power plant has been converted into a mega solar power generating station which poised to give a huge fillip to Indias renewable energy ambiti

examrobotsa's picture
Q: 32 (CDS-II/2009)
In a significant climate responsive project, in which one of the following places, recently an abandoned thermal power plant has been converted into a mega solar power generating station which poised to give a huge fillip to India’s renewable energy ambition?

question_subject: 

Geography

question_exam: 

CDS-II

stats: 

0,9,32,10,6,9,16

keywords: 

{'mega solar power generating station': [0, 0, 1, 0], 'thermal power plant': [0, 0, 2, 0], 'renewable energy ambition': [0, 0, 1, 0], 'rajasthan': [0, 0, 1, 18], 'orissa': [0, 0, 1, 0], 'significant climate': [0, 0, 1, 0], 'west bengal': [1, 0, 0, 3], 'india': [8, 1, 7, 13], 'jaisalmar': [0, 0, 1, 0], 'namrup': [0, 0, 2, 0], 'huge fillip': [0, 0, 1, 0]}

The correct answer is option 3, Jamuria in West Bengal. In this specific climate responsive project, an abandoned thermal power plant has been converted into a mega solar power generating station. This conversion is significant because it aligns with India`s renewable energy ambition.

Option 1, Talcher in Odisha, is not the correct answer as the thermal power plant conversion did not take place there. Similarly, option 2, Namrup in Assam, is also incorrect as the conversion did not occur in that location.

Option 4, Jaisalmer in Rajasthan, is also incorrect. Although Rajasthan is known for its solar power projects, in this scenario, the abandoned thermal power plant was not converted into a solar power generating station in Jaisalmer.

It is important to note that if you believe the provided answer is incorrect, it is advisable to double-check the information and provide the corrected answer.

Practice this on app