Change set
Pick exam & year, then Go.
Question map
Not attempted
Correct
Incorrect
★
Bookmarked
Loading…
Q11
(CISF/2019)
Miscellaneous & General Knowledge › Important Days, Places & Events
A can complete a work in 12 days. Bis 60% more efficient than A. The number of days taken by B to finish the same work is
Result
Your answer:
—
·
Correct:
C
Explanation
To find the time taken by B, we first determine the efficiency of both individuals. Efficiency is inversely proportional to the time taken to complete a work.
- Time taken by A = 12 days.
- Efficiency of A = 1/12 units per day.
- Since B is 60% more efficient than A, B's efficiency is 160% of A's efficiency: 1/12 × 1.6 = 16/120 = 2/15 units per day.
The number of days taken by B is the reciprocal of its efficiency:
TimeB = 1 ÷ (2/15) = 15/2 = 7.5 days
Converting 7.5 days into a mixed fraction gives 71⁄2 days. In the provided options, 72 is a typographical error representing 71⁄2. Therefore, option C is the correct choice.
How others answered
Each bar shows the % of students who chose that option.
Green bar = correct answer, blue outline = your choice.
Community Performance
Out of everyone who attempted this question.
100%
got it right
✓ Thank you! We'll review this.