Change set
Pick exam & year, then Go.
Question map
Not attempted
Correct
Incorrect
★
Bookmarked
Loading…
Q11
(CISF/2019)
Miscellaneous & General Knowledge › Important Days, Places & Events
A can complete a work in 12 days. Bis 60% more efficient than A. The number of days taken by B to finish the same work is
Explanation
To find the time taken by B, we first determine the efficiency of both individuals. Efficiency is inversely proportional to the time taken to complete a work.
- Time taken by A = 12 days.
- Efficiency of A = 1/12 units per day.
- Since B is 60% more efficient than A, B's efficiency is 160% of A's efficiency: 1/12 × 1.6 = 16/120 = 2/15 units per day.
The number of days taken by B is the reciprocal of its efficiency:
TimeB = 1 ÷ (2/15) = 15/2 = 7.5 days
Converting 7.5 days into a mixed fraction gives 71⁄2 days. In the provided options, 72 is a typographical error representing 71⁄2. Therefore, option C is the correct choice.
✓ Thank you! We'll review this.